Ascot Vale Leisure Centre – Spa and Sauna Project Works
Last updated: 14 October 2026
Project Type: Current project
Project works are being undertaken on the spa and sauna at the Ascot Vale Leisure Centre.
The project works comprise of significant renewal and upgrade works that are required to improve the safety, reliability, functionality and patron experience of the spa and sauna facilities.
The project works will deliver improvements including:
Spa
- Installation of new pipework between the spa and jet pumps in the plantroom.
- Construction and installation of a new balance tank, installation of a new skimmer, drain and suction grate.
- Relocation of the existing filtration pump and control panel.
- Upgrade to lighting in the spa plantroom.
Sauna
- Converting the existing two saunas into one large sauna.
- Construct and install new plant room walkway channel to house both spa and sauna plant controllers and pumps.
- Installation of new cedar cladding and seating.
- Installation of new heaters, lighting and flooring.
- Installation of new fixed cedar glazed windows.
- Installation of new plumbing and electrical works
These works involve substantial upgrades to the underlying mechanical, hydraulic and electrical systems that support the safe operation of the facilities. The project will improve operational efficiency, enhance patron comfort, and help ensure the spa and sauna remain functional and fit for purpose for many years to come.
Moonee Valley City Council acknowledges that the temporary closure and associated construction impacts may be inconvenient for some patrons. However, these works are considered essential to maintaining a safe, reliable and high-quality leisure facility for the community.
Get in touch with the project delivery team
Have a question? Reach out to our team
Project updates
Project update 14 October 2026
Project works are due to begin on 21 October 2026 with works scheduled to conclude late February 2027. Temporary barriers will be installed surrounding the work zone. The spa, sauna, steam room and pool deck showers will not be available during the works period.
Throughout the project, access to the 25m pool, warm water pool, learners pool, aquatic changerooms, family changerooms and accessible changerooms will be maintained at all times.
The spa, steam room and sauna facilities at the Keilor East Leisure Centre remain open for patron usage.
Additional Information
Current patrons
- Keilor East Leisure Centre’s spa, steam room and sauna facilities remain open for patron usage
- Free membership suspension available. Please submit an online form here
- Access to the Warm Water Pool will remain as usual. You can view the Warm Water Pool class timetable here
- If you have any additional questions, please email our membership service team via avlcenquiries@movemv.com.au
Accessing Ascot Vale Leisure Centre during the project works
The spa, sauna, steam room and pool deck showers will not be available during the works period.
Throughout the project, access to the 25m pool, warm water pool, learners pool, aquatic changerooms, family changerooms and accessible changerooms will be maintained at all times.